Question: A. What is the critical path for this project network? A-B-C-D-E-F-G-H A-C-F-H A-D-G-H B-E-G-H B. What is the probability that the critical path for this

A.
What is the critical path for this project network?
| A-B-C-D-E-F-G-H | ||
| A-C-F-H | ||
| A-D-G-H | ||
| B-E-G-H |
B. What is the probability that the critical path for this project will be completed within 75 weeks? (Please use decimal point format.)
Consider the following work breakdown structure