Question: a . What is the project's duration if only normal times are used? b . What is the minimum - cost schedule? c . What

a. What is the project's duration if only normal times are used?
b. What is the minimum-cost schedule?
c. What is the critical path for the minimum-cost schedule?
\table[[Activity,\table[[Normal],[Time],[(days)]],\table[[Nomal],[Cost ($)]],\table[[Crash],[Time],[(days)]],\table[[Crash],[Cost ($)]],\table[[Immediate],[Predecessor(s)]]],[A,6,1,000,5,1,200,-],[B,4,800,2,2,000,-],[D,3,600,2,900,A, B],[E,2,1,500,1,2,000,B],[F,2,900,4,1,200,C, D],[G,4,900,4,900,E],[H,4,500,2,900,G]]