Question: B. Minimum Cost Schedule (25 points). Information concerning a project is given in the table below. Activity Normal Normal Crash Crash Cost Immediate Time Cost

B. Minimum Cost Schedule (25 points). Information
B. Minimum Cost Schedule (25 points). Information concerning a project is given in the table below. Activity Normal Normal Crash Crash Cost Immediate Time Cost ($) Time ($) Predecessor(s) (days) (days) A 5 1000 4 1200 B 800 3 2000 C 600 900 A.B D 1500 2 2000 B E 900 3 1200 C.D F 1300 1400 E G 900 3 900 E H 5 500 3 900 G Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 14. a. What is the project's duration if only normal times are used? b. What is the minimum-cost schedule? c. What is the critical path for the minimum-cost schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!