Question: A work breakdown structure has been created. Activities have been identified and sequenced. A network diagram has been built. The project sponsor has asked you
A work breakdown structure has been created. Activities have been identified and sequenced. A network diagram has been built. The project sponsor has asked you what is the shortest amount of time in which the project can be completed. What do you do
A
Sum all possible sequenced paths to find the correct path on the network
B
You don't have enough information because the scope baseline hasn't been established yet
Find all possible sequenced paths in the network diagram, calculate each path's duration, and identify the path with the shortest overall duration
Find all possible sequenced paths in the network diagram, calculate each path's duration, and identify the path with the longest overall duration
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock