Question: A work package is expected to take 10 weeks to complete. Its budget is $2000. The work package is 50% complete, and $1500 has been

A work package is expected to take 10 weeks to complete. Its budget is $2000. The work package is 50% complete, and $1500 has been spent. What is the work package's earn value?

Group of answer choices

$500

$1000

$1500

$2000