Question: A work package is expected to take 10 weeks to complete. Its budget is $2000. The work package is 50% complete, and $1500 has been
A work package is expected to take 10 weeks to complete. Its budget is $2000. The work package is 50% complete, and $1500 has been spent. What is the work package's earn value?
Group of answer choices
$500
$1000
$1500
$2000