Question: A work package is expected to take 5 weeks to complete. Its budget is $100. It is end of the firstperiod,the work package is 20%
A work package is expected to take 5 weeks to complete. Its budget is $100. It is end of the firstperiod,the work package is 20% complete, and $40 has been spent. What is the schedule variance?
Step by Step Solution
There are 3 Steps involved in it