Question: A work package is expected to take 5 weeks to complete. Its budget is $100. It is the end of the first period, the work
A work package is expected to take 5 weeks to complete. Its budget is $100. It is the end of the first period, the work package is 20% complete, and $40 has been spent. What is the schedule variance?
Group of answer choices
$40
$5
$20
$15
$0