Question: A work package is expected to take 5 weeks to complete. Its budget is $100. It is the end of the first period, the work

A work package is expected to take 5 weeks to complete. Its budget is $100. It is the end of the first period, the work package is 20% complete, and $40 has been spent. What is the schedule variance?

Group of answer choices

$40

$5

$20

$15

$0