Question: A work system has five stations that have process times of 5,6,5,10 and 15. Find the bottleneck station. Add 2 machines to that station. What
A work system has five stations that have process times of 5,6,5,10 and 15.
Find the bottleneck station. Add 2 machines to that station.
What is the new bottleneck time ?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
