Question: A work system has five stations that have process times of 5,10,6,6 and 15. Find the bottleneck station. Add 2 machined to that station. What
A work system has five stations that have process times of 5,10,6,6 and 15.
Find the bottleneck station. Add 2 machined to that station.
What is the throughput time of the system ?