Question: A work system has five stations that have process times of 5, 9, 14, 9, and 8. What is the bottleneck time? Part 2 A.

A work system has five stations that have process times of 5, 9, 14, 9, and 8. What is the bottleneck time?

Part 2

A.

9

B.

14

C.

45

D.

35

E.

18