Question: (a) You are given the project network/precedence diagram below. Determine the critical path and show your work. A (5) (10) Start B (5) D (4)

(a) You are given the project network/precedence

(a) You are given the project network/precedence diagram below. Determine the critical path and show your work. A (5) (10) Start B (5) D (4) Finish F (9) C(6) Perform your calculations using the headings shown below: Path Time (b) Determine the ES, EF, LS, LF, & slack for each activity. Indicate which activities are on the critical path. On Critical (LS-ES) or Path? Activity (LF-EF) Indicate Activity Time | ES | EF L S Slack with a * LF