Question: Old MathJax webview Old MathJax webview This is what the whole problem looks like. The numbers inside the circles and their paths(A,B,C,...) are given. Please
Old MathJax webview


This is what the whole problem looks like. The numbers inside the circles and their paths(A,B,C,...) are given. Please look again.

Same as the look of this question. This is a question similar to my question. It might help.
Given: The network diagram shown below. Required: a) Identify the activity or activities, which are definitely critical, b) Explain the reasons for your choice. 2 I A G B F H K 6 7 9 C J E 4 00 Given: The network diagram shown below. Required: a) Identify the activity or activities, which are definitely critical, b) Explain the reasons for your choice. I F H K 4 8 (a) You are given the project network/precedence diagram below. Determine the critical path and show your work. A (5) E (10) Start B (5) D (4) Finish F (9) C (6)Step by Step Solution
There are 3 Steps involved in it