Question: A) You have a fixed-work task in Microsoft Project. The task has 2 full-time resources available for 8 hours each day, and it has a
A) You have a fixed-work task in Microsoft Project. The task has 2 full-time resources available for 8 hours each day, and it has a 5-day duration with 80 hours of work. What happens to the project in terms of the resource unit, work, or duration in the following scenario? Explain your answer.
1. If 1 full-time resource quit the project and you are unable to get a replacement.
2. If you find out that you have 4 days to complete the task rather than 5.
3. If you find out that the task will take 10 hours of additional work.