You can submit your work either as a Word fite, or an Excel file, or solve it on paper, take a picture, and upload it to Canvas Don't forget to explain your work! A PERT diagram for a project is given below: lo Start C End 2016 BB Assume that activity times of Start and End are zero. Activity times for each activity is given in the data table below. a. Calculate each "?" in the PERT diagram. (20 ?'s, 0.3 pts each, 6 pts total) b. Determine the critical path.(1 pts)