Question: A(7) B(10) Start F(2) C(5) D(4) E(9) Activity Cost per day to crash Number of days activity may be shortened crashed $250 1 $300 B

A(7) B(10) Start F(2) C(5) D(4) E(9) Activity
A(7) B(10) Start F(2) C(5) D(4) E(9) Activity Cost per day to crash Number of days activity may be shortened crashed $250 1 $300 B E 1 2 $600 For the above network diagram, the project indirect cost for each day is $1000. The table gives the crashing (also referred to as expediting) information. If you crash (expedite) this project to reduce the total time by one day, as long as the crashing cost per day is less than $1000, which activity should you crash? Activity B Activity Activity