ABC University is planning to offer a special programme for a Technology Adoption in Project Management. The programme coordinator of the University has classified various activities and their time estimates that must be done before conducting the programme. The coordinator has summarized all the activities as the following table. Activity A B C D E F G H I J Description Design brochure and course announcement Identify prospective module-convenors Prepare detailed outline of course Send brochure and students applications Send module-convenor applications Select module-convenor for the course Accept students Select text-book for course Order and receive text-books Prepare room for the class Preceding Activity (ies) A B C, E D F G, H G Activity Time (weeks) 7 8 4 18 10 4 7 7 11 4 You are assigned as the project manager for this project. You are requested to: a) construct the network diagram for the project. b) calculate the earliest and latest starting and finishing times for each activity and their slacks. c) determine the project's critical path and duration. ABC University is planning to offer a special programme for a Technology Adoption in Project Management. The programme coordinator of the University has classified various activities and their time estimates that must be done before conducting the programme. The coordinator has summarized all the activities as the following table. Activity A B C D E F G H I J Description Design brochure and course announcement Identify prospective module-convenors Prepare detailed outline of course Send brochure and students applications Send module-convenor applications Select module-convenor for the course Accept students Select text-book for course Order and receive text-books Prepare room for the class Preceding Activity (ies) A B C, E D F G, H G Activity Time (weeks) 7 8 4 18 10 4 7 7 11 4 You are assigned as the project manager for this project. You are requested to: a) construct the network diagram for the project. b) calculate the earliest and latest starting and finishing times for each activity and their slacks. c) determine the project's critical path and duration.
Expert Answer:
Answer rating: 100% (QA)
a Start 6 Activity A B D E F G H I J A B T Preceding Activity critical A B C E E F G H ... View the full answer
Related Book For
Introduction to Operations Research
ISBN: 978-1259162985
10th edition
Authors: Frederick S. Hillier, Gerald J. Lieberman
Posted Date:
Students also viewed these accounting questions
-
The facilities manager at Oxbridge University is planning to apply fertilizer to the grass in the quadrangle area in the spring. The grass needs nitrogen, phosphorus, and potash in at least the...
-
Calculate the work that must be done to charge a spherical shell of radius R to a total charge Q.
-
A company is planning to offer a discount for payment within 10 days to its customers, who currently pay after 45 days. Only 40 per cent of credit customers would take the discount, although...
-
State whether the following statements are true or false. Also, very briefly mention the reason if the statement is false. i. TOFO Surfactants increase the surface tension of water. ii. TOFO The Mach...
-
On February 1, 2011, the Xilon Corporation issued 5,000 shares of its nopar common stock in exchange for five acres of land located in the city of Monrovia. On the date of the acquisition, Xilon's...
-
A rectangular plate is rotating with a constant angular speed about an axis that passes perpendicularly through one corner, as the drawing shows. The centripetal acceleration measured at corner A is...
-
What are the advantages and disadvantages of taking a deposition?
-
The following note accompanied recent financial statements for Goodyear Tire and Rubber Company: We are a defendant in numerous lawsuits alleging various asbestos-related personal injuries purported...
-
A 10-year annuity-immediate with annual payments of 1000 is selling at 7537.63. If the required rate of return for Lucy is 6%, should she invest on this annuity or not
-
Alice J. and Bruce M. Byrd are married taxpayers who file a joint return. Their Social Security numbers are 123-45-6789 and 111-11-1111, respectively. Alice's birthday is September 21, 1966, and...
-
A car moving on a straight road covers and third of the distance with 20 km/hr & rest with 60 km/hr. The average speed is Let total distance travelled = x km and total time taken
-
Consider we replaced the laser with an incandescent flashlight; the intensity of the flashlight as it reaches the polarizers is 24 W/m. 1. With no background light, find the angle between the...
-
A gas stream comprising of air and vapour of an organic compound is to be scrubbed in an absorption tower for separation of organic compound by absorption in oil. The operation is countercurrent....
-
8) The figure shows the velocity-time graph of a particle which moves along a straight line from rest to rest in 30 seconds. The parts OA and AB are straight lines and the curve BC is an arc of the...
-
Four charged objects, A-D, are arranges on the corners of a rectangle with sides of length 3 cm and 6 cm, as shown in the figure. Objects A, C and D have charges of +8e. Determine the sign and...
-
We have the following information for Essilor Luxottica Introduction Income Statement Revenue ( ttm ) 1 . 0 6 B Revenue Per Share ( ttm ) 2 . 5 5 Quarterly Revenue Growth ( yoy ) - 3 . 6 0 %...
-
The U.S. Central Intelligence Agency maintains an online World Factbook that is a convenient source of a wide variety of geographic, social, and economic information. You may look up information by...
-
Smthe Co. makes furniture. The following data are taken from its production plans for the year. Required: 1. Determine the hazardous waste disposal cost per unit for chairs and for tables if costs...
-
You are given the following payoff table (in units of thousands of dollars) for a decision analysis problem: (a) According to Bayes decision rule, which alternative should be chosen? (b) Find EVPI....
-
Consider the 10-city traveling salesman problem whose links have the associated distances shown in the following table. 3 City 2 3 9 10 1 13 25 15 21 9 19 18 815 26 21 29 2 3 23 16 10 11 18 23 284 34...
-
Reconsider Prob. 7.3-4. After further negotiations with each vendor, management of the G.A. Tanner Co. has learned that either of them would be willing to consider increasing their supply of their...
-
A sensitive instrument of mass \(100 \mathrm{~kg}\) is installed at a location that is subjected to harmonic motion with frequency \(20 \mathrm{~Hz}\) and acceleration \(0.5 \mathrm{~m} /...
-
The force transmissibility of a damped single-degree-of-freedom system with base motion is given by Eq. (9.106): \[T_{f}=\frac{F_{t}}{k Y}=r^{2}\left\{\frac{1+(2 \zeta r)^{2}}{\left(1-r^{2}...
-
A viscously damped single-degree-of-freedom system has a body of mass \(25 \mathrm{~kg}\) with a spring constant of \(70 \mathrm{kN} / \mathrm{m}\). Its base is subjected to harmonic vibration. (a)...
Study smarter with the SolutionInn App