Question: 1. Draw the project network diagram and determine the normal time to complete the project, activity slack times, the critical path(s), and total project costs

1. Draw the project network diagram and determine the normal time to complete the project, activity slack times, the critical path(s), and total project costs (i.e., baseline your project) using Critical Path Method.
2. Determine the best way to crash the project to complete it in 35 weeks with revised activity slack times, critical path(s), and total project costs. Provide reasoning as to how all crashing decisions were made.
3. Activity times with the greatest uncertainty are Activities D, E, and H. Describe conceptually how you could model this uncertainty in activity times. (You do not have the necessary data to actually do this numerically.)
4. What are your final recommendations?

Step by Step Solution

3.27 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 2 The total cost to achieve a 35 weeks project completion date is 404167 by crashing A by 1 week B by 2 weeks H by 2 weeks and C by 1 week Notice th... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

546-B-M-L-O-M (4396).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!