Question: A,B,C,D,E,F weeks Suppose that Rafay is only given 10 weeks (instead of 12 ) to complete the project. By how many weeks should each activity

A,B,C,D,E,F weeks
Suppose that Rafay is only given 10 weeks (instead of 12 ) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration