Question: Accepted deliverables are an output from which process? Question 1 options: Collect Requirements Validate Scope Close Project or Phase Control Scope Question 2 ( 2

Accepted deliverables are an output from which process?
Question 1 options:
Collect Requirements
Validate Scope
Close Project or Phase
Control Scope
Question 2(2 points)
Deliverables that meet acceptance criteria are:
Question 2 options:
verified.
output from the control scope process.
passed by the quality control inspection.
formally signed off and approved by the customer or sponsor.
Question 3(2 points)
Work performance data output from the Validate Scope process include the following except:
Question 3 options:
the deliverables that were over budget.
the deliverables that have been accepted.
the deliverables that have finished.
the deliverables that have started.
Question 4(2 points)
The key benefit of the Control Scope process is it:
Question 4 options:
reduces rework.
verifies deliverables.
accepts deliverables.
allows the scope baseline to be maintained.
Question 5(2 points)
Control Scope process includes all of the following except:
Question 5 options:
formulating acceptance of completed project deliverables.
managing changes to the scope baseline.
monitoring the status of the product scope.
monitoring the status of the project scope.
Question 6(2 points)
The requirements traceability matrix:
Question 6 options:
helps to detect the impact of any change or deviation from the scope baseline on the project objectives.
is an output of the Validate Scope process.
is an output of the Control Scope process.
is an output of the Direct and Manage Project Work process.
Question 7(2 points)
The main difference from the Validate Scope process and the Control Quality process is:
Question 7 options:
Validate Scope is concerned with acceptance of deliverables and Quality Control is concerned with correctness of deliverables.
Validate Scope verifies deliverables while Quality Control verifies requirements.
Validate Scope is an input to Quality Control.
there is no significant difference.
Question 8(2 points)
An output of the Validate Scope process is:
Question 8 options:
accepted deliverables.
rejected deliverables.
validated deliverables.
verified deliverables.
Question 9(2 points)
Which is an input to the Monitor and Control Project Work process?
Question 9 options:
Validated changes
Validated deliverables
Accepted deliverables
None of the above
Question 10(2 points)
Requirements traceability matrix is not an input to the__________ process.
Question 10 options:
Validate Scope
All of the above
Define Scope
Control Scope

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!