Question: Accepted deliverables are an output from which process? Question 1 options: Collect Requirements Validate Scope Close Project or Phase Control Scope Question 2 ( 2
Accepted deliverables are an output from which process?
Question options:
Collect Requirements
Validate Scope
Close Project or Phase
Control Scope
Question points
Deliverables that meet acceptance criteria are:
Question options:
verified.
output from the control scope process.
passed by the quality control inspection.
formally signed off and approved by the customer or sponsor.
Question points
Work performance data output from the Validate Scope process include the following except:
Question options:
the deliverables that were over budget.
the deliverables that have been accepted.
the deliverables that have finished.
the deliverables that have started.
Question points
The key benefit of the Control Scope process is it:
Question options:
reduces rework.
verifies deliverables.
accepts deliverables.
allows the scope baseline to be maintained.
Question points
Control Scope process includes all of the following except:
Question options:
formulating acceptance of completed project deliverables.
managing changes to the scope baseline.
monitoring the status of the product scope.
monitoring the status of the project scope.
Question points
The requirements traceability matrix:
Question options:
helps to detect the impact of any change or deviation from the scope baseline on the project objectives.
is an output of the Validate Scope process.
is an output of the Control Scope process.
is an output of the Direct and Manage Project Work process.
Question points
The main difference from the Validate Scope process and the Control Quality process is:
Question options:
Validate Scope is concerned with acceptance of deliverables and Quality Control is concerned with correctness of deliverables.
Validate Scope verifies deliverables while Quality Control verifies requirements.
Validate Scope is an input to Quality Control.
there is no significant difference.
Question points
An output of the Validate Scope process is:
Question options:
accepted deliverables.
rejected deliverables.
validated deliverables.
verified deliverables.
Question points
Which is an input to the Monitor and Control Project Work process?
Question options:
Validated changes
Validated deliverables
Accepted deliverables
None of the above
Question points
Requirements traceability matrix is not an input to the process.
Question options:
Validate Scope
All of the above
Define Scope
Control Scope
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock