Question: According to the earned value management ( EVM ) process, in which of the following scenarios would the project manager and client need to reassess
According to the earned value management EVM process, in which of the following scenarios would the project manager and client need to reassess the assumptions of a project? More than one answer may be selected.
Check All That Apply
completing a critical task according to new client specifications would cause the project to go over budgetcompleting a critical task according to new client specifications would cause the project to go over budget
adding two additional developers to the project would reduce the schedule by half, resulting in an estimated percent increase in salesadding two additional developers to the project would reduce the schedule by half, resulting in an estimated percent increase in sales
a project manager determines that the project will not be completed on timea project manager determines that the project will not be completed on time
market research has determined that the product being worked on does not meet the needs of their target marketmarket research has determined that the product being worked on does not meet the needs of their target market
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock