Question: KENNY B. International Corporation builds radio frequency transponders for 40-foot containers. The most recent containers built requires 14 different activities. KENNY B. International would like

KENNY B. International Corporation builds radio frequency transponders for 40-foot containers. The most recent containers built requires 14 different activities. KENNY B. International would like to determine the total project completion time (in days) and those activities that lie along the critical path.

a. Complete the table below and make sure to indicate in the Cullumn:

Activity

Optimistic time

Most likely time

Pessimistic time

LF

ES

EF

?

?

?

?

A

4

6

7

5.83

0.00

5.83

B

1

2

3

11.83

0.00

2.00

C

6

6

6

11.83

5.83

11.83

D

5

8

11

17.67

5.83

13.83

E

1

9

18

21.00

11.83

21.00

Step by Step Solution

3.40 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the total project completion time and identify the activities along the critical path w... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!