Question: KENNY B. International Corporation builds radio frequency transponders for 40-foot containers. The most recent containers built requires 14 different activities. KENNY B. International would like
KENNY B. International Corporation builds radio frequency transponders for 40-foot containers. The most recent containers built requires 14 different activities. KENNY B. International would like to determine the total project completion time (in days) and those activities that lie along the critical path.
a. Complete the table below and make sure to indicate in the Cullumn:
Activity | Optimistic time | Most likely time | Pessimistic time | LF | ES | EF | ? | ? | ? | ? |
A | 4 | 6 | 7 | 5.83 | 0.00 | 5.83 | ||||
B | 1 | 2 | 3 | 11.83 | 0.00 | 2.00 | ||||
C | 6 | 6 | 6 | 11.83 | 5.83 | 11.83 | ||||
D | 5 | 8 | 11 | 17.67 | 5.83 | 13.83 | ||||
E | 1 | 9 | 18 | 21.00 | 11.83 | 21.00 |
Step by Step Solution
3.40 Rating (169 Votes )
There are 3 Steps involved in it
To determine the total project completion time and identify the activities along the critical path w... View full answer