| Activity | Predecessor | Time (minutes) | Workstation |
| A | - | 3 | 1 |
| B | - | 4 | 2 |
| C | A | 3 | 3 |
| D | A | 2 | 4 |
| E | B, C | 1 | 5 |
| F | B | 4 | 6 |
| G | C | 2 | 5 |
| H | D, F | 4 | 7 |
| I | D, F | 3 | 8 |