Question: Balance the assembly line using longest task time. What is the efficiency of your solution? 4. A cheese processing plant has several tasks that
"Balance the assembly line using longest task time."
" What is the efficiency of your solution?"


4. A cheese processing plant has several tasks that need to be done as listed in the following table with time for each activity and precedence relationships.The line works 5 days a week, for 8 hours each day. The plant provides cheese to several supermarket chains at a rate of 600 Ibs per week. Activity Predecessor Time (minutes) Workstation A B 2 C A D A .A E B. C F B G C H DE D. FActivity Predecessor Time (minutes) Workstation E 4 9 K F 8 L 1.J 10 M K 4 a. Balance the assembly line using longest task time. b. What is the efficiency of your solution
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts