Question: A.Create a network diagram for the project below. What is the critical path and duration? (Hint your diagram should have the three paths listed in

A.Create a network diagram for the project below. What is the critical path and duration? (Hint your diagram should have the three paths listed in the responses below, and your path completion times should be identical to those in the respones below)

Activity Duration Predecessor(s)
A 2 ---
B 5 ---
C 3 ---
D 2 A
F 3 D
E 3 C
G 4 B, E
J 3 G

BGJ 12

CEGJ 13

ADF 7

All of the paths are critica

b.Which activities in the project need to be completed for the project to be complete?

BGJ 12

CEGJ 13

ADF 7

All of them

c.Activites ________ have ______ days of slack

A, D & F, 6

B 3

C, E, G & J 13

A & B 2

d.The latest start and latest finish dates for activity D are

2, 4

8, 10

10, 13

2, 8

e.What happens if activity F actually takes 7 days instead of 3?

The project completion will be delayed 4 days

The project completion will be delayed 7 days

The project completion will not be affected

The critical path shifs to ADF

f.Before the project, we receive revised estimates of 6 for activity A and 5 for activity D. What effect does this have?

The project completion will be delayed 11 days

The project completion will be delayed 6 days

The project completion will not be affected

The critical path shifs to ADF and the project completion estimate increases to 14 days

g.In order to buffer our project against uncertainty in activity completion times (the possibility that an activity time will exceed its estimate), we should place a feeder buffer ___ and a project buffer.

Before F, before J

Before E, after F & J

Before G, after F & J

After F, before J

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!