Question: Activi ty Normal Duration (hours) Normal Cost ($) Crash Duration (hours) Crash Cost (S) Immediate Predecessors A 5 10 3 20 None B 3 15
Activity | Normal Duration (hours) | Normal Cost ($) | Crash Duration (hours) | Crash Cost (S) | Immediate Predecessors |
A | 5 | 10 | 3 | 20 | None |
B | 3 | 15 | 2 | 23 | A |
C | 6 | 25 | 3 | 31 | B |
D | 3 | 20 | 1 | 24 | C |
E | 7 | 30 | 4 | 45 | C |
F | 2 | 5 | 1 | 10 | C,E |
G | 8 | 35 | 6 | 50 | F |
H | 10 | 50 | 7 | 80 | D,G |
Can you determine the absolute shortest time to finish this project (i.e., after having performed a maximum crashing possible)? What is the total cost of such crashing? Fully explain your analysis.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
