Q1: Sarah Watson, Chairman of Watson Company has developed a table for the tasks, its duration and predecessor relationships are given in the table for a new project. (Marks-15, CLO-3) a. Develop AON network b. Identify the critical path c. Calculate the project completion time d. Develop Gantt chart for the project Activity Immediate Predecessor(s) T'ime(weeks) A 9 B A 7 A 3 D B 6 E B 9 F 4 E,F 6 H D 5 I G,H 3