Question: Activities A,B, and C are the immediate predecessors for Y activity. If the earliest finishing time for the three activites are 13,16 , and 11

 Activities A,B, and C are the immediate predecessors for Y activity.
If the earliest finishing time for the three activites are 13,16 ,
and 11 , then what will be the earliest starting time for

Activities A,B, and C are the immediate predecessors for Y activity. If the earliest finishing time for the three activites are 13,16 , and 11 , then what will be the earliest starting time for Y ? 11 16 13 Cannot bo dotermined What is the PERT time (Te) with optimistic, most likely, and pessimistic time estimations of 8,10,12 days 5 10 7 12 A new loch corrpary hires Matthew for the position of sottware programmor to work on their new projoct. The salary ped to Matthew by the coneary would be an exathle of which type of costs? Dived. Indrect Research Intarighter

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!