Question: Activities A,B, and C are the immediate predecessors for Y activity. If the earliest finishing time for the three activites are 13,16 , and 11


Activities A,B, and C are the immediate predecessors for Y activity. If the earliest finishing time for the three activites are 13,16 , and 11 , then what will be the earliest starting time for Y ? 11 16 13 Cannot bo dotermined What is the PERT time (Te) with optimistic, most likely, and pessimistic time estimations of 8,10,12 days 5 10 7 12 A new loch corrpary hires Matthew for the position of sottware programmor to work on their new projoct. The salary ped to Matthew by the coneary would be an exathle of which type of costs? Dived. Indrect Research Intarighter