Question: Activities A B C D E F G (5) H J Predecessor START START START A B C D,E F G I Duration 8
Activities A B C D E F G (5) H J Predecessor START START START A B C D,E F G I Duration 8 4 3 5 8 7 3 2 2 4 Resources 4 4 3 2 3 1 2 st 4 2 3 Q1 Using the table perform the optimum resource leveling resource constraint scheduling. The maximum designers on any given should be 6. Q2 Draw Network diagram and calculate duration of all paths.