Question: Activities Duration Immediate predecessors 10 None B 5 None C 5 None D 8 A E E 6 B F 5 A G 7 C

Activities Duration Immediate predecessors 10
Activities Duration Immediate predecessors 10
Activities Duration Immediate predecessors 10 None B 5 None C 5 None D 8 A E E 6 B F 5 A G 7 C H 10 D 1 4 F J 7 E,G,J K 1 J questions Which of the following represents the critical path through this project B-E-J-K A-F-1-1-K A-D-H C-G-J-K C-G-I-K