Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 10 -- B 8 A C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 10 | -- |
| B | 8 | A |
| C | 4 | A |
| D | 2 | B |
| E | 6 | C,D |
Select one:
A. A-C-E; 26
B. A-D-E; 26
C. A-B-E; 20
D. A-B-D-E; 26
E. A-B-D-E; 20
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
