Question: please answer all 5 question. Activities Duration Immediate predecessors 10 None B B 5 None 5 None D 8 A E E 6 B F
please answer all 5 question.
Activities Duration Immediate predecessors 10 None B B 5 None 5 None D 8 A E E 6 B F 5 A G 7 C H 10 D 1 4 F J 7 E,G,J K 1 J 1.Which of the following describe paths through your network? 2. How much time will be required to complete this project? 3.What is the earliest you could possibly start on activity J, given that you started work on the project right now? 4. Which of the following represents the critical path through this project? 5. What is the total amount of slack in this project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock