Question: Activities G , P , and R are the immediate predecessors for activity W . If the earliest finish times for the three are 1

Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12,15, and 10, then the earliest start time for W is
10
12
15
Cannot be determined