Question: Question 1 ( 2 . 5 points ) Listen The earliest finish time for the final activity is the project duration. Question 1 options: a
Question points
Listen
The earliest finish time for the final activity is the project duration.
Question options:
a True
b False
Question points
Listen
Activities with zero slack
Question options:
a have no predecessors.
b must be completed first.
c can be delayed.
d lie on a critical path.
Question points
Listen
The earliest start time for an activity is equal to the smallest of the earliest finish times for all its immediate predecessors.
Question options:
a True
b False
Question points
Listen
An activity has an Optimistic activity time of days, a Most Probable activity time of days, and a Pessimistic activity time of days. The average or expected time for the activity is
Question options:
a
b
c
d
Question points
Listen
An activity in a project network cannot begin until all of the activities leading into that activity have been completed.
Question options:
a True
b False
Question points
Listen
The path in a project network with the average duration is the critical path.
Question options:
a True
b False
Question points
Listen
Activities K M and S immediately follow activity H and their latest start times are and The latest finish time for activity H
Question options:
a is
b is
c is
d cannot be determined.
Question points
Listen
The slack of an activity is the difference between the latest finish and the earliest finish times.
Question options:
a True
b False
Question points
Listen
Activities G P and R are the immediate predecessors for activity W If the earliest finish times for the three are and then the earliest start time for W
Question options:
a is
b is
c is
d cannot be determined.
Question points
Listen
Noncritical activities are distinguished by the presence of
Question options:
a idle resources.
b zero slack.
c wasted time.
d slack.
Question points
Listen
When making a backward pass through a project network, you must start at the finish node.
Question options:
a True
b False
Question points
Listen
Which of the following is always true about a critical activity?
Question options:
a LF LS
b LS EF
c EF ES
d ES LS
Question points
Listen
All activities on a critical path have zero slack time.
Question options:
a True
b False
Question points
Listen
The critical path
Question options:
a is the shortest path.
b is any path that goes from the starting node to the completion node.
c is the longest path.
d is a combination of all paths.
Question points
Listen
One of PERT's bold assumptions is that
Question options:
a individual activity times are constant.
b individual activity times are uncertain.
c individual activity times can be added together.
d individual activity times are dependent of each other.
Question points
Listen
The slack of any activity is the amount of time that the activity can be delayed without delaying the completion of the project.
Question options:
a True
b False
Question points
Listen
Arcs in a project network indicate
Question options:
a completion times.
b precedence relationships.
c durations.
d the critical path.
Question points
Listen
A forward pass is the process of moving forward through the project network to determine the latest start times and latest finish times of each activity.
Question options:
a True
b False
Question points
Listen
Arcs in a project network indicate
Question options:
a completion times.
b the critical path.
c precedence relationships.
d activities
Question points
Listen
The purpose of the forward pass in the Critical Path Method technique is to
Question options:
a Review each of the precedence relationships in the activity network.
b To calculate the slack time within each node on the activity network.
c To determine the earliest time each activity can start and finish.
d To determine the latest time each activity can start and finish.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock