Question: Activities G,P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12,15 , and 10 ,

Activities G,P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12,15 , and 10 , then what is the earliest start time for W ? 10 12 15 cannot be determined