Question: Activities Normal Time Normal Cost Crash Duration Crash Cost A 9 days $8,000 8 days $12,000 B 5 days $6,000 3 days $10,000 C 12
Activities Normal Time Normal Cost Crash Duration Crash Cost A 9 days $8,000 8 days $12,000 B 5 days $6,000 3 days $10,000 C 12 days $9,000 11 days $12,000 36. Which activity should be the next activi