Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 2 -- B 4 -- C
The critical path for the network activities shown below is ________ with duration ________.
Activity
Duration
Immediate
Predecessors
A
2
--
B
4
--
C
6
A,B
D
1
A,B
E
2
B,C,D
Activity
Preceding
Optimistic
Probable
Pessimistic
A
--
5
11
14
B
-
3
3
9
C
--
6
10
14
D
A, B
3
5
7
E
B
4
6
11
F
C
6
8
13
G
D, E
2
4
6
H
F
3
3
9
a. Calculate the expected duration and variance of each activity.
b. Calculate the expected duration and variance of the critical path.
c. Calculate the probability that the project will be completed in less than 28 weeks.
Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
Activity
Normal Time
Normal Cost
Crash Duration
Crash Cost
X
8 days
$6,000
6 days
$8,000
Y
3 days
$1,800
2 days
$2,400
Z
12 days
$5,000
9 days
$7,700
a. What is the crash cost per unit time for each of the three activities?
b. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
c. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?