Question: Activities Predecessor Expected Duration ( weeks ) 1 1 2 1 3 3 1 4 4 2 , 3 3 5 2 6 6 4

Activities Predecessor Expected Duration (weeks)
11
213
314
42,33
526
64,51
75,66
Calculate the TE (earliest expected completion time), TL (latest expected completion time) and Slack for each activity