Question: Activities Preq. Duration A n/a 2 B n/a 6 C n/a 4 D A 3 E C 5 F A 4 G B,D;E 2 Find
| Activities | Preq. | Duration |
| A | n/a | 2 |
| B | n/a | 6 |
| C | n/a | 4 |
| D | A | 3 |
| E | C | 5 |
| F | A | 4 |
| G | B,D;E | 2 |
Find the completion time, critical path and slack times in the above project. ii. If overtime is considered for the workers, each activity is completed 1/4 of its normal duration early. However, overtime wages are 1.5 times the daily normal wage of 100 TL, i.e. 150 TL. On the other hand, you are allowed to increase the project completion cost by 2/5 at the most. If you exercise this, will the new completion times, critical path and activity costs change or how will they change
Could you please provide a solution.
Thank you very much