Question: Activities Preq. Duration A n/a 2 B n/a 6 C n/a 4 D A 3 E C 5 F A 4 G B,D;E 2 Find

Activities Preq. Duration
A n/a 2
B n/a 6
C n/a 4
D A 3
E C 5
F A 4
G B,D;E 2

Find the completion time, critical path and slack times in the above project. ii. If overtime is considered for the workers, each activity is completed 1/4 of its normal duration early. However, overtime wages are 1.5 times the daily normal wage of 100 TL, i.e. 150 TL. On the other hand, you are allowed to increase the project completion cost by 2/5 at the most. If you exercise this, will the new completion times, critical path and activity costs change or how will they change

Could you please provide a solution.

Thank you very much

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!