Question: Consider a project that has been modeled as in Table1. Table 1: Activities and Predecessors Activity Immediate Predecessors Duration A 7 B A 6 C
Consider a project that has been modeled as in Table1. Table 1: Activities and Predecessors Activity Immediate Predecessors Duration A 7 B A 6 C A 3 D B,C 14 F DE 5 a. draw the PERT/CPM network for this project and determine the projects expected completion time and its critical path b. suppose the standard deviation of the activity duration are....