Consider a project that has been modeled as in Table1. Table 1: Activities and Predecessors Activity Immediate Predecessors Duration A 7 B A 6 C A 3 D B,C 14 F DE 5 a. draw the PERT/CPM network for this project and determine the projects expected completion time and its critical path b. suppose the standard deviation of the activity duration are....

Question shows as the following pictureConsider a project that has been modeled as in

1. Consider a project that has been modeled as in Table 1. Table 1: Activities and Predecessors Activity Immediate Predecessors Duration A 7 B A 6 A 3 D B,C 12 E B,C 14 F DE 5 - = 2, and of a. Draw the PERT/CPM network for this project and determine the project's expected completion time up and its critical path. b. Suppose the standard deviations of the activity durations are o A 1, OB = 1, 0c 0, op = 1, OE 1. Then please estimate the standard deviation of the overall project's standard deviation op. c. Suppose for the standard Normal random variable Z, we know P[-1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!