Question: Activity C is directly preceded by two activities, activity A and activity B, Activity A has an expected time of 5 and ES time of

Activity C is directly preceded by two

Activity C is directly preceded by two activities, activity A and activity B, Activity A has an expected time of 5 and ES time of 6. Activity B has an expected time of 7 and an ES time of 7. Activity C has an expected time of 10. The ES for activity C is 21 O 14 11 24 10