Question: Activity A; 6 days; IP = none Activity B; 18 days; IP = none Activity C; 15 days; IP = A Activity D; 23 days;
Activity A; 6 days; IP = none Activity B; 18 days; IP = none Activity C; 15 days; IP = A Activity D; 23 days; IP = A, B Activity E; 12 days; IP = B Activity F; 38 days; IP = C Activity G; 24 days; IP = D Activity H; 38 days; IP = E Activity K; 10 days; IP = F, G Activity M; 7 days; IP = G, H
The earliest start time of activity K is at the end of day __________.