Question: Activity A; 6 days; IP = none Activity B; 18 days; IP = none Activity C; 15 days; IP = A Activity D; 23 days;

Activity A; 6 days; IP = none Activity B; 18 days; IP = none Activity C; 15 days; IP = A Activity D; 23 days; IP = A, B Activity E; 12 days; IP = B Activity F; 38 days; IP = C Activity G; 24 days; IP = D Activity H; 38 days; IP = E Activity K; 10 days; IP = F, G Activity M; 7 days; IP = G, H

The earliest start time of activity K is at the end of day __________.

Activity A; 6 days; IP = none Activity B; 18
Question 2 The information about a project with 10 activities is shown below. Activity A; 6 days; IP = none Activity B; 18 days; IP = none Activity C; 15 days; IP = A Activity D: 23 days; IP = A, B Activity E; 12 days; IPB Activity F: 38 days; IP =C Activity G: 24 days; IP =D Activity H; 38 days; IP = E Activity K; 10 days; IP = F, G Activity M; 7 days; IP = G, H The earliest start time of activity K is at the end of day 2 ODO DOO FO BIN F F6 F7 A & $ 4 % 5 6 7 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!