Question: 3 Question 3 10 pt The information about a project with 10 activities is shown below. Activity A; 19 days; IP = none Activity B;

3 Question 3 10 pt The information about a
3 Question 3 10 pt The information about a project with 10 activities is shown below. Activity A; 19 days; IP = none Activity B; 29 days; IP = none Activity C; 45 days; IP = A Activity D; 23 days; IP = A, B Activity E; 42 days; IP = B Activity F; 36 days; IP = C,D Activity G; 17 days: IP = C, D Activity H; 27 days; IP = E Activity K; 10 days; IP = F Activity M; 14 days; IP = G, HI The latest start time of activity D is at the end of day