Question: Activity (A ) activity time (6) weeks [Immediate Predecessor (none) Activity (B ) activity time (5) weeks [Immediate Predecessor (none) Activity (C ) activity time
Activity (A ) activity time (6) weeks [Immediate Predecessor (none)
Activity (B ) activity time (5) weeks [Immediate Predecessor (none)
Activity (C ) activity time (3) weeks [Immediate Predecessor (A)
Activity (D ) activity time ( 3) weeks [Immediate Predecessor (B)
Activity (E ) activity time ( 6) weeks [Immediate Predecessor (C,D)
Activity (F ) activity time ( 9) weeks [Immediate Predecessor (D)
a) Draw the network diagram for this project. b) Identify the critical path. c) Calculate the expected project length.