Question: Activity A and Activity B MUST be complete before Activity C can start A. Network A B. Network B C. Network C D. Network D

Activity A and Activity B MUST be complete before

Activity A and Activity B MUST be complete before Activity C can start

A. Network A

B. Network B

C. Network C

D. Network D

Earliest Start time for Activity B is equal to the Earliest Finish time for Activity A while the Earliest Finish time for Activity B is equal to the Earliest Start time for Activity C.

A. Network A

B. Network B

C. Network C

D. Network D

Both Activities A and B MUST be complete before Activity C OR Activity D can start.

A. Network A

B. Network B

C. Network C

D. Network D

Earliest Finish time for Activity A is equal to the Earliest Start time for Activity B and also equal to the Earliest Start time for Activity C.

A. Network A

B. Network B

C. Network C

D. Network D

Looking at only Network A, assume the time to complete Node A is 10, Node B is 7, and Node C is 6, then the EF for node C is:

A. 13

B. 20

C. 16

D. 10

Further to question 7 and Network A, LF for Node B is

A. 10

B. 3

C. 7

D. 16

Use the four network diagram pictures below to answer the following questions Q 3-8: b. b d. Network A Network B b b Network C Network D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!