Question: Activity A B C D E F Activity Predecessor - - - Time ( weeks ) A A B C 5 8 3 7 6

Activity
A
B
C
D
E
F
Activity Predecessor
---
Time (weeks)
A
A
B
C
5
8
3
7
6
D, E
10
Using Table 9.1, the critical path for this project consists of activities
A-B-D-F.
O A-C-E-F.
A-B-C-F.
A-B-C-D-E-F