Question: Activity A B C D E F Duration 2 days 6 days 7 days 3 days 4 days 4 days 14 days 3 days B

Activity A B C D E F Duration 2 days 6 days 7

Activity A B C D E F Duration 2 days 6 days 7 days 3 days 4 days 4 days 14 days 3 days B A B D E F G D H E F G 1. Construct a precedence table & network diagram of the above project. 2. Find the Durations & Critical Path of the project