Question: 1. The project duration is: * None 16 22 25 .......... 2. The slack time of activity E is: * 0 None 8 9 .......
1. The project duration is: *
None
16
22
25
..........
2. The slack time of activity E is: *
0
None
8
9
.......
3. The slack time of activity F is: *
8
2
0
None
......
4. The CP contains: *
B, E, G
None
C, F, H
A, D, G
.....
5. The duration of activity A is: *
None
9
5
8
....
6. The variance of activity C is: *
None
2.7
1
1.7
......
7. The project standard deviation is: (Take one number after the comma) *
1
1.8
None
2.6
.......
8. What is the probability to finish the project before 25 weeks: *
92.2%
90.2%
95.15%
none