Question: 1. The project duration is: * None 16 22 25 .......... 2. The slack time of activity E is: * 0 None 8 9 .......

1. The project duration is: * None 16 22 25
1. The project duration is: *
None
16
22
25
..........
2. The slack time of activity E is: *
0
None
8
9
.......
3. The slack time of activity F is: *
8
2
0
None
......
4. The CP contains: *
B, E, G
None
C, F, H
A, D, G
.....
5. The duration of activity A is: *
None
9
5
8
....
6. The variance of activity C is: *
None
2.7
1
1.7
......
7. The project standard deviation is: (Take one number after the comma) *
1
1.8
None
2.6
.......
8. What is the probability to finish the project before 25 weeks: *
92.2%
90.2%
95.15%
none
A network consists of the following list. Times are given in weeks. Preceding Pessimis 16 6 9 Activity A B C D E F G H Optimistic 6 2 3 4 2 6 3 4 A B, C D, E, F F Most 8 4 3 8 5 10 5 6 12 | 8 14 7 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!