Question: Activity A B C D E F G H Optimistic Time 3 5 2 2 1 3 7 2 Most Pessimistic Immediate Likely Timel Time

Activity A B C D E F G H Optimistic Time 3 5 2 2
Activity A B C D E F G H Optimistic Time 3 5 2 2 1 3 7 2 Most Pessimistic Immediate Likely Timel Time Predecessor(s) 4 5 7 9 3 10 A 5 8 B 7 7. B 5 7 CD 8 9 DE 6 10 F (a) What is the expected duration of the project? (b) What is the project variance? (c) If the deadline of the project is 25 days, what is the probability of finishing the project on time? IF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!