Question: Activity A B. C D E F G H Predecessors None A A B, C B D CI E, F, G Description Contract signing Questionnaire

Activity A B. C D E F G H Predecessors None A A
Activity A B. C D E F G H Predecessors None A A
Activity A B. C D E F G H Predecessors None A A B, C B D CI E, F, G Description Contract signing Questionnaire design Target market ID Survey sample Develop presentation Analyze results Demographic analysis Presentation to client Estimated Duration 5 6 13 6 9 2 [2] What is the time estimate of an activity in which the optimistic time is 5 days, the likely time is 8 days, and the pessimistic time is 14 days? Show your work