Question: Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1000, is 50% complete, and actually cost $700 so far.

Activity A is worth $500, is complete, and

Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1000, is 50% complete, and actually cost $700 so far. Activity C is worth $100, is 75% complete, and has actually cost $90 so far. Which of the following gives the remaining amount to be spent on the project based on current spending efficiency? Cost variance Budget remaining Estimate To Complete (ETC) O Cost Performance Index (CPI) )